Toward 2018 launch

UAE nuclear programme edges

Themuslimchronicle, themuslimchronicle

Themuslimchronicle, themuslimchronicleUAE nuclear programme edges

Christer Viktorsson
Abu Dhabi - Muslimchronicle

At first glance, the long hallway seems abandoned. But behind glass walls, in soundproof offices, engineers and physicists are putting the final touches to the Arab world's first nuclear programme.

At the Federal Authority for Nuclear Regulation (FANR) in Abu Dhabi, dozens of employees are reviewing the 15,000-page application for the Barakah Nuclear Energy Plant, scheduled to launch next year.

Located just across the Gulf from Iran, which is home to a controversial nuclear programme of its own, the Barakah plant will make the UAE the first Gulf state to have a peaceful nuclear energy programme.

By 2020, the UAE Peaceful Nuclear Energy Program will be in full gear, with four nuclear reactors providing nearly 25 percent of the UAE's electricity needs, according to the state-run Emirates Nuclear Energy Corporation (ENEC).

The first reactor was initially set to start generating power in 2017, but ENEC recently announced its inauguration would be delayed until 2018 for technical reasons.

"We received the application for reactor one in March 2015 and since then we have been studying it," said Christer Viktorsson, director general at the Federal Authority for Nuclear Regulation which oversees regulation and licensing for the UAE's nuclear programme.

Viktorsson says the federal authority has sent ENEC more than 1,000 questions seeking documented answers since 2015 -- and the licensing process is not yet over.

"It's a massive application," he told AFP. "There are a few areas where we still have questions."

"We have to verify... that they have security plans, like emergency plans, and if an accident happens they can deal with it."

- Concerns in volatile Gulf -

In the FANR offices, 300 kilometres (185 miles) west of the Barakah plant, Emirati and foreign employees are buried in licensing paperwork in a bid to meet next year's deadline.

ENEC in April reported construction of the plant's four units had been 80 percent completed, with reactor one at 95 percent completion.

Operations teams and contingency plans are also in place, according to ENEC, and Viktorsson says he has "no doubt" that the company will meet the 2018 launch date.

Much of the construction of the $25-billion (21.2-billion-euro) Barakah plant has been outsourced to the Korea Electric Power Corporation, the largest electric utility in South Korea, which won the project over French multinational group AREVA.

"We don't think the nuclear power plant will cause any problems in the region," said a South Korean diplomat in the UAE, requesting anonymity.

"The Barakah nuclear power plant will play an important role for the UAE's economic development and will be a role model for the other Arab countries, proving that nuclear power can be used for peaceful purposes."

While the peaceful use of nuclear energy is far from new, the UAE nuclear programme has raised some concerns in the Gulf, a region that has long been gripped by war and political crises.

But officials in the UAE, which sits on seven percent of the world's oil reserves, say their programme will not add fuel to fire in the region, where the latest diplomatic crisis has seen gas-rich Qatar isolated from the UAE and Saudi Arabia over allegations that the emirate is too close to Iran and harbours Islamist extremists.

"Our country is and will remain a forerunner," a UAE official said on condition of anonymity.

UAE ally Saudi Arabia has also said it aims to develop a peaceful nuclear energy programme.

- No uranium enrichment -

Civilian safety remains a concern, and residents living inside a 50-kilometre (30-mile) radius of the Barakah plant have been instructed on procedure in case of an accident.

But concerns about safety reach far beyond the UAE's borders: the Barakah plant is about 50 kilometres east of the border with Saudi Arabia, some 320 kilometres west of Oman and 350 kilometres south of Iran.

In addition to evacuation drills for residents, Viktorsson says, FANR has held seminars joining representatives of the UAE, Oman and Saudi Arabia.

And amid a war of words between Iran and the United States over Tehran's nuclear programme, the UAE has said it will not be developing an uranium enrichment programme or nuclear reprocessing technologies.

"I know that nuclear for many means the non-peaceful parts, but in this country the nuclear law, for example, talks about peaceful purposes and we have a programme which checks all nuclear activities," said Viktorsson.

"If there are suspicions, we interfere immediately."

source: AFP

themuslimchronicle
themuslimchronicle

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

uae nuclear programme edges uae nuclear programme edges

 



Themuslimchronicle, themuslimchronicle

GMT 15:49 2017 Tuesday ,04 April

Europol, Georgia sign pact to combat terrorism

GMT 17:34 2017 Saturday ,19 August

India rail accident kills 10

GMT 07:44 2017 Saturday ,19 August

Firms flock to Syria fair with eye on reconstruction

GMT 18:11 2016 Saturday ,03 December

Congress and Trump agree to turn the heat up on Iran

GMT 13:12 2017 Tuesday ,05 December

Lebanon's PM Hariri withdraws his resignation

GMT 08:39 2017 Friday ,17 November

Baidu speeds up AI progress

GMT 03:33 2017 Tuesday ,21 February

Deadly blast strikes demonstration in Kabul

GMT 10:04 2011 Sunday ,11 September

Vauxhall/Opel to unveil 2-seat electric car at IAA

GMT 05:16 2016 Tuesday ,30 August

Fukushima Nuclear Plant Prepares for Typhoon

GMT 20:05 2011 Saturday ,27 August

Egyptair resumes Baghdad flights after 21 years

GMT 19:35 2011 Tuesday ,26 July

Ozil : Real \'more mature\' this season

GMT 05:41 2017 Thursday ,09 March

El Jaish Win Qatar Men's Basketball League

GMT 22:04 2011 Thursday ,08 September

Museum of the great syrian revolution monument

GMT 11:15 2015 Thursday ,01 October

Thuraya's CEO named Satellite Executive Of 2015

GMT 14:08 2016 Wednesday ,16 November

Scientists fear the worst under a Donald Trump presidency

GMT 10:28 2017 Wednesday ,12 April

New York $40mn attraction puts world in miniature

GMT 23:41 2017 Wednesday ,12 April

Easier visa regime to boost Oman tourism

GMT 17:48 2012 Monday ,09 January

Business trip: Dubai

GMT 01:34 2017 Tuesday ,11 April

Oman takes part in Arab Labour Conference in Egypt

GMT 15:20 2017 Monday ,05 June

Libya cuts all diplomatic ties with Qatar
Themuslimchronicle, themuslimchronicle
Themuslimchronicle, themuslimchronicle
 
 Themuslimchronicle Facebook,themuslimchronicle facebook  Themuslimchronicle Twitter,themuslimchronicle twitter Themuslimchronicle Rss,themuslimchronicle rss  Themuslimchronicle Youtube,themuslimchronicle youtube  Themuslimchronicle Youtube,themuslimchronicle youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2023 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2023 ©

muslimchronicle muslimchronicle muslimchronicle muslimchronicle
themuslimchronicle themuslimchronicle themuslimchronicle
themuslimchronicle
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
themuslimchronicle, themuslimchronicle, themuslimchronicle